Goliath Complex
Project information
As at 31 December 2022
Description
As at 31 December 2022
Multi-deposit complex comprising the Goliath, Goldlund, and Miller deposits. Located approximately 20 km east of Dryden, Ontario, with access to the Trans-Canada Highway, CP Rail, and Hydro One infrastructure. Property consists of approximately 35,092 hectares. Feb-2023 PFS outlines a 13-year LOM producing ~90 koz Au/yr at AISC US$1,072/oz, initial capex C$335M, after-tax NPVâ‚… C$336M / IRR 25.4% at US$1,750/oz Au. 2025 programme: 25,000 m infill drilling at Goldlund underway. Key risks: permitting and First Nations consultation ongoing.
Mining metrics
Multiple effective dates · exclusive