Description
As at 31 December 2025
Open-pit gold mine with 2.5 Mtpa crush-grind carbon-in-leach (CIL) processing operation. Acquired June 17, 2025 via Calibre Transaction. First gold pour September 2025; commercial production end of November 2025. Q4 2025 throughput 90% of 6,850 tpd nameplate. Q4 2025 production 23,207 oz Au at cash cost $1,579/oz, AISC $1,588/oz. Phase 2 expansion being advanced. Ramp to nameplate expected by Q2 2026. NI 43-101 Technical Report filed March 30, 2026.
Mining metrics
As at 31 December 2025 · exclusive
Premium access required
This content is available on a paid plan.
Upgrade to Premium to unlock this content.
Reserves & resources — detail
As at 31 December 2025
Premium access required
This content is available on a paid plan.
Upgrade to Premium to unlock this content.