CCL Midscale Trains 8 & 9 Project
Data compiled from public filings — information only, not investment advice. AI‑assisted; see methodology.
Project information
As at 31 December 2025
Description
As at 31 December 2025
Two additional midscale Trains expected to add approximately 5 mtpa of LNG production capacity once fully completed, inclusive of estimated debottlenecking opportunities. Positive FID on June 17, 2025 with full notice to proceed issued to Bechtel effective June 18, 2025. Overall project completion 31.8% as of December 31, 2025 (engineering 75.5%, procurement 47.3%, subcontract 29.0%, construction 0.2%); expected substantial completion 2H 2028. FERC siting/construction authorization received March 2025; non-FTA DOE export authorization pending; 170 Bcf/yr FTA authorization (July 2023) effective from first commercial export.
Processing facilities
As at 31 December 2025
Premium access required
This content is available on a paid plan.
Upgrade to Premium to unlock this content.
Copyright © 2026, Metal Pilot
We use strictly necessary cookies for authentication and site functionality. Optional analytics (Google Analytics) load only after you accept; we do not use advertising, remarketing, or Google Signals. We honour Global Privacy Control (GPC) and other recognised opt-out signals by keeping analytics off for that browser.