High-Pressure Acid Leaching (HPAL) facility under construction in Sorowako (East Luwu Regency, South Sulawesi) to produce mixed hydroxide precipitate (MHP) for EV batteries. JV partner PT Huali Nickel Indonesia (HLNI), in partnership with global partner Huayou (slurry pipeline component). Project commenced June 2024; construction at 17% by end-2025; first production targeted 2027. Progress on autoclave fabrication, land acquisition for the 45.3 ha FPP facility, completion of HLNI Material Storage Yard at Waru Waru and Enggano Ports, and slurry pipeline route evaluation in mining areas. Mining feed sourced from Sorowako Block limonite (IGP Sorlim).