Jansen
Project information
As at 30 June 2025
Description
As at 30 June 2025
100%-owned potash project in Saskatchewan. Jansen Stage 1 (4.15 Mtpa) is 68% complete; capex estimate increased from US$5.7B to US$7.0-7.4B (including contingencies) with first production reverting to the original mid-CY2027 schedule. Jansen Stage 2 (incremental 4.36 Mtpa) is 11% complete; execution extended two years with first production shifting from FY2029 to FY2031; JS2 capex under review. Reserves/resources stated for the Lower Patience Lake unit; reserve metallurgical recovery 88%; %K2O equivalent to %KCl using factor 1.583.
Mining metrics
As at 30 June 2025 · inclusive